First progress update from Watkin Road, our 609-bed student scheme for YourTRIBE in Wembley 🏗️
South Block is two towers, 27 and 18 storeys. Slip form is finished on one core and the second will be done in the next few weeks. The RC frame is now going up, and SFS starts next month.
North Block is 21 storeys. The frame should be finished in about six weeks, with SFS and windows following on behind. Brickwork has started at the lower levels, and our own drylining and M&E teams are already inside on fit-out. The first bedroom furniture arrives next month.
Not the easiest site, right next to Wembley Stadium, but having our own people on the frame, drylining and M&E helps a lot.
Thanks to YourTRIBE, the design team and everyone on site.